Due to both slabs being poured incorrectly we have had to get our Structural Engineer to design a new framing as well as roofing plan, versus “figuring it out in the field (extra cost to us). It looks good but it’s going to require the GC to cut, excavate and pour new footings. We have asked and are trying to get our GC to have this accomplished before the end of the week since our Structural Engineer is going out-of-town for several days.