Well, they drilled the foundation slab today to check for grade beams and guess what? Yep, no grade beams!! It mustn’t matter that they were in the construction plans and highly important, they just didn’t pour them. Okay, now we’re getting past serious, he’s basically building a structure that could put my family and/or our friends in danger. Forget for a moment the fact that 5-10 years down the road we would have all sorts of issues with a foundation that’s crumbling and walls collapsing, this mistake could seriously put my family at risk of injury or worse. These were designed to support the family room above the kids play room, family room with a FIREPLACE. Apologies for ranting but how do you miss these? And you want more? He wants to charge us for it – said that for him to change anything it would be considered a “change order“. All of this is because he wouldn’t remove his original mistake. QUESTION, is there a word for someone who is beyond incompetent?
It only gets worse, the carport foundation (supposed to be retaining) wall which has already been poured twice isn’t deep enough, meaning that we will need to adjust the slab in the carport as well as the framing plan for the deck and outdoor room. We asked the GC if he would remove it and pour a new one at the correct depth and as a retaining wall and of course he said no.
And, we also found out on our own today that we will need a new water-line as well as sewer line due to roots.
Our Structural Engineer is still trying to reach our GC to discuss the framing options but once again he said that he would have time to meet with her and every time she brings it up when they’re meeting about other items he always says that he has to go. She’s basically doing this by herself, I guess he meant it the other day when responding to one of his subs he said ” I don’t know, she’s the one in charge”, referring to our Structural Engineer.
And of course our GC and architect didn’t respond to my email asking for them to work with our Structural Engineer to design a framing plan to utilize all of the mis-ordered lumber that is sitting on our property and basically going to waste. I would just hate for all of this to be taken to a landfill. As for our architect, I was a huge fan but that is starting to fade, I’m not sure what’s going on but from what I’ve been gathering there is absolutely no coordination or communication between him and our GC.
Absolute last statement, it has always bugged me why our GC would work 2-3 days on our project and then move to another. After talking with a few people in the industry it was their opinion that he is basically banking one job on another. Working on a job and collecting a check once a certain phase is completed and then using that money to pay for the next job – similar to kiting a check. Not sure if this is the case but it sure would make sense.
Enough for today, I’m done, worn out mentally and emotionally.